Add projects and tasks to the Project Center timeline in Project Online

The timeline at the top of the Project Center provides a simple way to show all of the projects and major tasks going on in your organization. You can use this timeline to craft a visual executive summary of your portfolio of projects.

Note: In addition to Project Center, adding tasks to the Schedule page timeline is another option available in Project Web App.

  1. On the Quick Launch, click Projects.

    Art for Multiple Timeline articles

  2. Click anywhere on the timeline you wish to add a project to, and then click the row header for the desired project.

    2nd multiple timeline pic

  3. On the Projects tab, in the Timeline group, click Add Project or Add Tasks.

    MultipleTimelines02 - Add Project

    If you are just adding a project, continue to step 4, but if you are adding tasks, select the task row(s) that you want to add to the timeline, and then click OK.

    MT04 - Select Task

    Tip: Don’t see the task you wanted to add? Try expanding the summary tasks in the Task Name column to drill down to the subtask level(s).

  4. To add another timeline, click the current timeline, and then click Add in the Timeline Bar group on the Timeline tab.

    Note: Multiple timelines are available in Project Online and Project Server 2016.

    MT05 - Add Another Timeline

  5. To move projects between timelines, click the project, and then click Move Up or Move Down in the Current Selection group on the Timeline tab.

    MT11 - Move Up/Down

Need more help?

Want more options?

Explore subscription benefits, browse training courses, learn how to secure your device, and more.

Communities help you ask and answer questions, give feedback, and hear from experts with rich knowledge.

Was this information helpful?

What affected your experience?
By pressing submit, your feedback will be used to improve Microsoft products and services. Your IT admin will be able to collect this data. Privacy Statement.

Thank you for your feedback!

×