Have been waiting for this feature for so long. When having a single
task or milestone driven by two or more Start to Finish dependencies the
dependant task is driven but newest date. That seems not to be logical,
would think it should be the oldest date. A exampel is that you have a
number of task ...
@NancyatMSFT - The workaround for this is users in our org are looking
into other tools. The lack of the functionality listed below is stifling
the adoption of Project for the Web.Inability to restrict user access
within plan.No global task fieldsGlobal Project, Resource and Task
fields must be inte...
@SayedNasr thanks for your feedback on this - the ability to manage what
a user can/can't do is something we've been looking into and we'll keep
your concerns in mind. What workarounds do you use today for this sort
of issue?
@TracyAllenUNB There have been some comments about making features Role
based and allowing configuration of what each Role can and cannot do. It
would be good to know that consideration is being given to this and that
configuration could, for example, allow for project team members to to
view all as...