@SakshiMunjal It is currently 5/9/2024. The screenshot below shows the
plan is "On track" and the baseline finish has already passed. What am I
missing?
@PetrKrenzelok - You would set your Scheduling Mode to 'Fixed Effort'.
Using this mode if you edit duration or edit the resources, the effort
will remain the same. Scheduling modes - Project for the web | Microsoft
Learn. Also, baselines are rolling out and the task level baseline
effort values are ...
We need some field for an Estimated effort, which does not change. Task
duration is a different thing. It is set automatically in relation to
the task start / end date. In our case it is 1 month long sprint. When I
set an Effort to say 10 MD, and then I start to fill in an assignments,
it resets tho...